Crystal River Nuclear Plant - Concrete Delamination
Investigation
In September 2009, a gap (delamination) was detected in the 42" thick
concrete containment structure at the Crystal River Nuclear plant.
The containment building wall is engineered to hold in a sudden buildup
of heat, pressure or steam inside the reactor building. Just inside the
wall is a steel-plate liner three-eighths of an
inch thick. The concrete is reinforced with a post-tensioned cables
located near the outside face.
The gap was discovered as workers cut a 25- by 27-foot hole in
the
containment wall so two huge steam generators could be removed and
replaced. The utility cut the hole because the reactor building's
regular equipment hatch is too small for the generators, which weigh
550 tons each.
The plant was not operating at the time, and there was no release of
radiation.
Cutting the hole required cutting a large number of PT cables
and removing the concrete with high pressure water cutters.
Due to the sensitivity of the structure, a thorough investigation into
the causes was required before any repairs were allowed.
The owner assembled a team of experts in the construction and nuclear
industries to determine the "Root Cause" of the failure and and create
a comprehensive report for the
Nuclear Regulatory Comission (NRC).
Dr Avi Mor was the lead concrete expert on the Root Cause
team.
The investigation determined that the delamination occured as a result
of detensioning the PT cables in preparation for the concrete removal.
The resulting stresses exceeded the capacity of the concrete
that had limited tensile strength due to its composition (mainly the
aggregates used).
(see
explanation by NRC)
Before any repairs could be attempted, a complete Non-Destructive
investigation of the structure determined the location and scope of the
delamination. Complex finite element analysis was performed
by others to determine how future detensioning and retensioning of
cables must be done in order to prevent a repeat of the delamination
during the repair process.
The delaminated area concrete was removed and new concrete was placed
in the gap.
However, the retensioning process appears to have caused new
delaminations in part sof the
original structure - prompting a new
evaluation of the future of the plant.
At this time (July 2011) the owner is still attempting to come up with
a new repair methodology that will allow the plant to continue
operations for more than twenty years.