If I understand correctly, your problem is that the whole concrete floor is moving 0.001" per day. If that is the case it may be necessary to reinforce the foundations after investigating the soils. This should be done by a local soils/structural engineer.
I assume that the machines are not just moving over the floor because that would probably be fixed by bolting !?
By the way, how do you measure such movement? Relative to what?
Interesting problem but I believe you need to get a local expert. If you need help locating one I may be able to help with that.
Laingsburg, U.S.A.
I am constructing a garage floor 7 foot below my original floor --my local building permit requires --how much weight will the upper floor support ?(Autos).
The floor is 21 x 25 foot concrete slab which is poured over a metal sheeting. this sheeting is placed across the 25 ft. span --overtop (3) 4 x 6 inch I-beams running the 21 ft. span, with an opening of 6 ft between each I beam... the concrete will be 4.5 inches thick with 1/4 inch re-bar in it. I have a drawing of the idea if you need more info. Please let me know as soon as possible-- so as I can get my permit approved and can get started on the construction. Thank you!
Thanks Doc!
I was hoping to once again skirt the long arm of the building inspector-- but your right-- I need to do this right the FIRST time. Thanks for the speedy info! Gary
I'm running out of time trying to find a company to provide a sub-bid for some very flat concrete work (finished product FF50) that has done some superflat (2-FF75's) work in the last 3 years. Can you do this? If not, do you know a company that can? Job is only 18,900 sf (2 slabs) and is near Sacramento, CA. It bids 15 October 1996. We can do good flatwork but we specialize in treatment plants which only requires the use of a mechanical screed instead of a laser screed as required for this work.
The only local company that is quoting this work was involved in writing the spec's and is quoting to all general contractors on this project.
Bidding has been extremely tight lately and I need an edge to better my chances of getting this project. Can you help? Please call me at (???) ///-//// .... Thank-you for your time and help.
Adana, Turkey
Dear sir, madam
we have poured the slab it was 35 centigrade degree. After pouring I
face with cracks although I use burlaps to cover it (cracks nearly 1/8
inches). How can I avoid these cracks and after pouring how frequently
do I have to water it? Can I water it in the afternoon? (here
traditionally they say to water only in the morning and in the evening.
Not in hot afternoon. Also there are no cracks within beams and columns
- only on the slab and there is leakage through the sub floor and salt
color tracks of the leakage. Although this problems I face with, I can't
even hammer a steel nail on the slab it is so hard. Does it show that no
structural problem?
Well it was surprise for me to find something like that web site. It is amazing. I would like to express my gratitude to you.
Dear M.A.,
This is a very common problem, even though yours sounds a little on the severe side.
In general, these are shrinkage cracks, caused by rapid loss of water from the fresh concrete while it hydrates and dries. Higher quality (stronger) concrete uses less water and will experience less shrinkage. Reinforced concrete will experience the shrinkage, but the steel will hold the cracks together and you will not have those wide cracks.
As to your specific situation.
1. Pouring concrete at high temperatures requires special care. 35 degrees Celsius (95 deg F) is very hot and will cause the concrete to dry faster with larger cracks. To minimize that problem you should use stronger concrete (less water) and start misting the surface as soon as it appears dry. Do it very carefully since you do not want to disturb the "skin" before it hardened, or add water to the fresh concrete. At these temperatures, normal concrete will probably be hard enough after 3-4 hours, but that depends on admixtures used in your area.
2. Covering with burlap is good practice if you keep it moist at all times, and apply it before the concrete lost too much water.
3. The reason for watering in early morning and evening is to save water. When you water around noon time, the heat will cause the water to evaporate almost instantly instead of penetrating and soaking the concrete. However, if you water the burlap and cover with plastic sheets you may overcome that problem.
4. I assume that your slab is placed directly on the ground without any steel. These are not structural slabs and will not "collapse." They will, however, remain cracked and cause many problems inside the house. If you plan to use floor tiles, the cracks might show through the tiles and cause them to crack too. The salt deposits you observed (efflorescence) are an indication that moisture is coming through. These will not stop and might get worse.
5. One thing you can do to minimize the cracks is to reinforce the slab. In the USA we use welded wire-mesh (steel wires welded to form a "net" with square holes) to arrest the cracks. In more severe situations we will also use steel rebars centered in the slab.
6. The most basic method of dealing with this problem is to provide "joints" at regular intervals. These joints are pre-cut "cracks" that force the cracking to happen where you want it and in straight lines. The joints can be cut by a concrete saw as soon as the concrete is strong enough to allow the equipment on top (but not later because it will start cracking...), or placed in the concrete during pouring by scoring the fresh concrete to about 1/3 of depth. Joints should be placed every 10-15 feet (3-4.5 meters) and divide the slab into square sections.
Hope that helps. If you have access to publications of the American Concrete Institute (ACI) you can find many sources that will help you further.
My name is < > and I am in the process of having a home built.
We are early in the construction phase with the decking and walls up.
Today we received approximately 1 inch of rain, thoroughly soaking
the rough-framed structure. While I believe the 3/4 inch TIG (tongue in
groove) OSB material will withstand the soaking, I am concerned about
the 3/4 inch TIG plywood which was used as decking material in the main
room.
Is there any way to know if separation will occur before I install the
oak hardwood flooring over it. The plywood is not of an exterior nature
but I have been told by my general contractor that it does contain
exterior-type glue. Any comments you could provide would be appreciated.
If the manufacturer did not certify his material for external use
then I would hesitate to accept your contractor's word. You may want to
contact the supplier/manufacturer for their opinion. You will usually
find stamps on the plywood that include all the information you need.
I suspect, however, that a single soaking is not the end of the world.
Allow it to dry completely and check it again. If it did not separate,
then it most likely will not unless repeatedly going through wetting and
drying cycles.
Will your contractor put his money where his mouth is? Will he post
a bond to guarantee his work?
I assume that simply replacing a few sheets of plywood at this time may
be worthwhile considering the costs involved with any other option if
failure occurs later.
I hope that helped.
We live in an area of Los Angeles where the water table is very high. During
the recent rains, the garage flooded. Clean water slowly seeped in on all sides
of the garage, where the floor and cement meet. After the rain, all that water
found it's way back out. The whole thing is a mystery to me. Where is this water
coming from? What can we do to keep the water out? Are you able to come see it
and give me some advice? If so, I would greatly appreciate it. We live in the
mid-Wilshire area (near the La Brea Tar Pits).
Thank you so much.
Very informative web site!
Los Angeles
The first thing I would be looking at is the landscaping around the garage.
Make sure that its level is below the floor level and that the drainage system
works.
If that is not the problem, then you may have ground water accumulating under
the garage during rain, and developing pressure because of runoff from higher
neighbors or landscaping. Since the garage slab is not sealed to the side walls
(by design) the gap may be enough for water to come through under pressure.
Solving this problem is a two step process:
1. Prevent water buildup under the garage. This is done by providing drainage
around the perimeter using "French Drains" installed at the footings level.
However, this may also be expensive, depending on your landscaping and yard. 2.
An alternative, or second measure, would be to seal/caulk the gap around the
perimeter of the slab. For proper application, you will have to clean the gap
very thoroughly, route it to at least a 1/8" wide by 1/2" deep groove, and use
an epoxy-based sealant/caulk to fill it. Preparations and applications MUST
follow the manufacturer's instructions to the letter!
I have a concern regarding the interior. I would not expect the same flooding
since the slab is usually sealed to the walls in the living area, and a special
water-proofing membrane (Visqueen) is applied under it. However, if the water
level and pressure are that high you may have some seepage under the
carpets/linoleum, or hardwood flooring. Given time, you may develop some nasty
mold or just ruin the flooring. You may want to try lifting the edge of carpets
at the corners and look for white salty deposits or black moldy areas.
Regardless of what you find, you should do something to improve the drainage
from the yard including maintenance type clearing of drain pipes. You should
also check with your neighbors to see if the problem is widespread, in which
case you may be able to share the cost of investigating.
Good Luck
I am putting a hot water heated concrete floor in my garage and I am wondering if it is a good idea to put insulation under it? I have been getting mixed opinions about this. I would also like to know if it is worth putting fiber in it if I am also using rods?
P.S. We live in northern WI.
I can understand why you are getting mixed opinions. The right choice depends on additional information I need.
1. Is that a slab-on-grade? If so then it depends on the soil for
support. If you use some sort of insulation between the concrete and
the soil it can weaken the system.
However, if when you said you are using "rods" (reinforcing bars?) you
meant that it is a structural slab which can stand on its own then the
support is not critical. Was it designed by a structural engineer?
2. If you can find insulation that is strong enough to support the weight of the concrete and your cars without crushing then I see no reason to worry. But if that insulation is going to deform in any way it will damage the concrete.
3. As for fibers - depends...
If you are adding fibers in order to gain some strength then forget it.
They don't.
If the purpose is to reduce the cracking in the slab then there are
better ways to do it, especially when you have reinforcing bars (or is
it wire mesh?)
Fibers add complications in the placing of the concrete and I see no
benefit in your case. You should however consider cutting joints that
will split the slab into sections that are no bigger than 15x15 ft.
After the concrete matures (3-6 months) you can seal the joints and
forget about them.
What were the concerns others had about the insulation? Let me know if there is additional information about the slab and what you decided to do.
Hello, Can you tell me what code says about cracks in a new construction home slab? We are having a house build and the slab started showing cracks (some 12 foot long) after just a few days. We have been told not to worry about them, but are afraid of them getting worst.
Orlando, FL
Aurora, USA
I need to build a 7'x7' 6 inch thick concrete slab for a spa/hot tub. The grade from an existing slab to the outside edge (7 feet) of the proposed slab drops 19.5 inches. I assume I need to build a retaining wall. Is my assumption correct? If so, can I use 6"x6"x8' landscape timbers? also, are there any other considerations I should be aware of?
R.,
The answer to that depends on the soil conditions, but most likely you will need some sort of retaining system..
My first choice would be to build the slab with "thickened edges" that serve as footings. On the sloped side you would make these edges go deeper into a trench in the soil all the way down to "solid base." If you make the "footings" 8" wide by 7' long by 30" deep (guesstimate) you may need an extra 1/2 yard of concrete, but will end up with a much stronger and stable system. It would be better to use at least 2 rebars at the top and bottom of the footings (length wise) and additional rebars to tie the slab to the footings directly. The slab itself will also benefit from rebars in both directions placed about half depth of the concrete. Common spacing is 1 foot on-center. If you extend those bars into the footings you will have a very strong and stable system.
A spa can be significant load on the base and may require recommendations from an engineer who is familiar with your soil conditions.
I am assuming you are planning to add fill material in order to create a level base for the concrete. Make sure this fill is very well compacted and stable before placing any concrete on it. Otherwise it could deform under the load of a full spa and cause the concrete to crack.
I am building a 1500 sf garage and want to install a heated floor system in it. My concrete contractor wants to use a two foot square re-bar grid and my heated floor contractor wants to use sheets of wire mesh. They both agree either system would work but they want me to be the deciding factor. It's my understanding re-bar would be stronger but wire mesh would work. Can you help me with this decision? I live in the mid-west, so mother nature may be a factor, it can be 100 in the summer and -40 in the winter.
Glenwood, USA
HI
We had a garage fire the garage was 32X48 We have been told we can lay a
new 3" concrete on top of the old after the fire. Then we were also,
told that we could build the building on the old concert and pour the
new concert inside the build on top of the old concert. we live in
northern MN so we also have a weather issue. Could you please help ?
Thanks you
Grand Forks
I am concerned about the post-tension slab method of slab
construction for our new church. I am the pastor and several folks, I
don't know why, came to me with concerns about this type of slab. The
slab is hexagonal with a diameter of 79 ft. But the architect has only
called for 4 inches of concrete. Is this adequate? The concerns are
about cracking once tension is applied since the thickness is only 4
inches. Do we need to be concerned?
I think most of the problem lies with us since none of us have any
experience with this type of concrete slab construction. Any information
you might be able to send our way would be greatly appreciated.
Thanks in advance for your help,
D.
Panam City, FL
Barton City, Michigan